- Maintained & improved 90 miles of dirt and gravel roads by cleaning borrow ditches to enhance water shedding and road stability.
- Re-established road crowns & graded surfaces to direct water runoff effectively.
- Hauled & stockpiled commercial ¾” road base, transporting materials deep into eroded sections via off-road dump trucks.
- Placed, graded, watered, & roller-compacted materials to restore heavily worn areas.
- Ensured all work met FP-14 standards & was completed within approximately 100 days, despite winter weather conditions & challenges.